150 workers were engaged to finish a piece of work in a certain no. of days. four workers dropped the second day, 4 more workers dropped the third day and so on.....it takes 8 more days to finish the work now.. find the no. of days in which the work was completed.

2 Answers

206
Sayantan Hazra ·

Try doing it with the concept of work - days.

Let x be the no. of days in which the piece of work would be originally finished by 150 workers.

Now, from ques, 150 workers work for 1 day, 146 for the 2nd day, 142 for the 3rd day and so on......

So, this becomes an AP of as 150, 146, 142, ......... and so on with (x + 8) terms.......since the workers will have to work for 8 more days now.

Therefore,

150x = sum of above AP till (x + 2) terms

→ 150x = (x + 8)2 (2*150 + (x + 8 - 1)(-4))

Solve this to get x.

Then, find x + 8.

206
Sayantan Hazra ·

think of it in this manner. ...if 10 ppl finish up a work in 5 days, then 1 man would require 10*5 = 50 days to complete the same work

Here too, we evaluate the net work that will be done by 1 person.....